10402 1/2 N MCCLEMONT AVE 91042

Certificate Information: 10402 1/2 N MCCLEMONT AVE 91042

Application / Permit
25016-20000-21007
Plan Check / Job No.
B25VN19200
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: EXISTING 2-CAR GARAGE TO BE CONVERTED INTO ADU PER GCS 66323(a)(1). ALL WORK PER WFPP. AND NEW 8'-6" X 18'-8" PATIO COVER ADDITION PER P/BC 2023-006
Permit Issued
Issued on 8/9/2025
Issuing Office
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2025 APPLICANT
Assigned to Plan Check Engineer 7/9/2025 LUISANGEL VALENZUELA
Corrections Issued 7/9/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 7/25/2025 LUISANGEL VALENZUELA
Plan Check Approved 8/1/2025 LUISANGEL VALENZUELA
Issued 8/9/2025 APPLICANT
CofO in Progress 5/4/2026 NICHOLAS TROWBRIDGE
Permit Finaled 6/9/2026 RUBEN SALAS
CofO Issued 6/9/2026 RUBEN SALAS
Permit Finaled 6/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/17/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/17/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/18/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/31/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 7/31/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/11/2025 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 9/12/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 9/17/2025 Approved WILLIAM WREN
Deputy Wood Construction 9/25/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/29/2025 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 9/29/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Approved WILLIAM WREN
HVAC-Rough 9/29/2025 Approved WILLIAM WREN
PLUMBING-Rough 9/29/2025 Approved WILLIAM WREN
Insulation 10/6/2025 No Access for Inspection DAVID ANDERSON
Interior/Exterior Lathing 10/6/2025 No Access for Inspection DAVID ANDERSON
Shower Pan 10/6/2025 No Access for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 10/8/2025 Approved WILLIAM WREN
Insulation 10/8/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 10/8/2025 Partial Approval WILLIAM WREN
Shower Pan 10/8/2025 Approved WILLIAM WREN
Drywall Nailing 10/10/2025 Approved MICHAEL CORTEZ
Final 4/9/2026 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 4/9/2026 Approved NICHOLAS TROWBRIDGE
Final 4/23/2026 Corrections Issued NICHOLAS TROWBRIDGE
Service/Power Release 4/23/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 4/27/2026 OK to Issue CofO NICHOLAS TROWBRIDGE