19757-19759 W GRESHAM ST 91324

Certificate Information: 19757-19759 W GRESHAM ST 91324

Application / Permit
25016-20000-20770
Plan Check / Job No.
B25VN18902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONVERT (E) ATTACHED GARAGE AND PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 66333. REMODEL (E) BEDROOM TO WIDEN CLOSET DOOR.
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2025 APPLICANT
Assigned to Plan Check Engineer 7/7/2025 ISIS ARGUETA
Corrections Issued 7/7/2025 ISIS ARGUETA
Plan Check Approved 8/2/2025 ISIS ARGUETA
Issued 8/18/2025 APPLICANT
CofO in Progress 5/7/2026 CHRIS CHRISTENSEN
Permit Finaled 5/11/2026 JOHN JANSON
CofO Issued 5/11/2026 JOHN JANSON
Permit Finaled 5/11/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/22/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/22/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/22/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/10/2025 Partial Approval CHRIS CHRISTENSEN
Wood Frame 12/24/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/9/2026 Approved CHRIS CHRISTENSEN
HVAC-Rough 2/9/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 2/9/2026 Approved CHRIS CHRISTENSEN
Wood Frame 2/9/2026 Partial Approval CHRIS CHRISTENSEN
Insulation 2/25/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/25/2026 Partial Approval CHRIS CHRISTENSEN
Wood Frame 3/4/2026 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 3/10/2026 Approved CHRIS CHRISTENSEN
Shower Pan 3/10/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/25/2026 Partial Approval CHRIS CHRISTENSEN
Sewer 4/21/2026 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/29/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/29/2026 Approved CHRIS CHRISTENSEN
Final 4/29/2026 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/29/2026 Approved CHRIS CHRISTENSEN
Green Building Rough 4/29/2026 Approved CHRIS CHRISTENSEN
HVAC-Final 4/29/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/29/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 4/29/2026 Approved CHRIS CHRISTENSEN
Final 5/6/2026 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved CHRIS CHRISTENSEN