19134-19136 W CHASE ST 91324

Certificate Information: 19134-19136 W CHASE ST 91324

Application / Permit
25016-20000-20736
Plan Check / Job No.
B25VN18888
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert (E) Attached Garage (415 sf) and enclose covered roof area for Addition (32 sf) to convert to Attached Accessory Dwelling Unit (447 sf) per Ordinance LAMC 12.22 A.33 (c) and (e) . Work per Wood Frame Prescriptive Provisions .
Permit Issued
Issued on 8/13/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2025 APPLICANT
Assigned to Plan Check Engineer 7/7/2025 KELVIN CHUONG
Corrections Issued 7/7/2025 KELVIN CHUONG
Applicant returned to address corrections 7/30/2025 GEORGE ALVAREZ
Applicant returned to address corrections 8/6/2025 GEORGE ALVAREZ
Plan Check Approved 8/10/2025 GEORGE ALVAREZ
Issued 8/13/2025 APPLICANT
CofO in Progress 2/23/2026 DAVID SCANTLIN
Permit Finaled 2/23/2026 JOHN JANSON
CofO Issued 2/23/2026 JOHN JANSON
Permit Finaled 2/23/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/11/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/11/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/12/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/18/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 10/2/2025 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 10/6/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 10/8/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/14/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 10/14/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Rough 10/14/2025 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 10/14/2025 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 11/20/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Rough 11/20/2025 Not Ready for Inspection KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 11/20/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/24/2025 Partial Approval KRISTEN CAUSEY
Insulation 12/2/2025 Approved KRISTEN CAUSEY
Drywall Nailing 12/8/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/8/2025 Approved KRISTEN CAUSEY
Shower Pan 12/8/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/6/2026 Approved KRISTEN CAUSEY
Final 2/6/2026 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 2/6/2026 Approved KRISTEN CAUSEY
Green Building Rough 2/6/2026 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 2/6/2026 Approved KRISTEN CAUSEY
Final 2/13/2026 Corrections Issued ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved ROBERT GOLD
ELECTRICAL-Final 2/18/2026 Corrections Issued HENRY KIM
Final 2/18/2026 Corrections Issued HENRY KIM
Gas Test 2/18/2026 Corrections Issued HENRY KIM
HVAC-Final 2/18/2026 Approved HENRY KIM
PLUMBING-Final 2/18/2026 Approved HENRY KIM
ELECTRICAL-Final 2/20/2026 Approved DAVID SCANTLIN
Final 2/20/2026 OK to Issue CofO DAVID SCANTLIN
Gas Test 2/20/2026 Approved DAVID SCANTLIN