9837-9839 N BELMAR AVE 91324

Certificate Information: 9837-9839 N BELMAR AVE 91324

Application / Permit
25016-20000-20665
Plan Check / Job No.
B25VN18846
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO 484 SQ.FT JUNIOR ACCESSORY DWELLING UNIT AND 68 SQ.FT CLOSET FOR SFD.
Permit Issued
Issued on 7/17/2025
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2025 APPLICANT
Assigned to Plan Check Engineer 7/7/2025 ARTIN ZARUKIAN
Corrections Issued 7/11/2025 ARTIN ZARUKIAN
Building Plans Picked Up 7/14/2025 APPLICANT
Plan Check Approved 7/17/2025 ANGELICA MARTINEZ
Issued 7/17/2025 APPLICANT
CofO in Progress 12/5/2025 DAVID SCANTLIN
Permit Finaled 12/12/2025 JOHN JANSON
CofO Issued 12/12/2025 JOHN JANSON
Permit Finaled 12/12/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/11/2025 WALLIE JONG
Sewer availability Cleared 7/11/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/12/2025 BRYAN GODINEZ

Contact Information

Contractor Power Home Builders; Lic. No.: 1107125-B 24007 VENTURA BLVD 230      CALABASAS, CA 91302
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2025 Corrections Issued HENRY KIM
Pre-Inspection 7/31/2025 Partial Inspection HENRY KIM
Footing/Foundation/Slab 8/7/2025 Approved KRISTEN CAUSEY
Underground Mechanical 8/21/2025 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 9/12/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/12/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 9/12/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 9/12/2025 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 9/18/2025 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 9/18/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/23/2025 Approved DAVID SCANTLIN
Green Building Rough 9/23/2025 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 9/23/2025 Approved DAVID SCANTLIN
Insulation 9/24/2025 Approved DAVID SCANTLIN
Drywall Nailing 10/1/2025 Approved KRISTEN CAUSEY
Final 11/21/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 11/21/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/21/2025 Approved DAVID SCANTLIN
Final 12/5/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 12/5/2025 Approved DAVID SCANTLIN