8230-8232 N MAMMOTH AVE 91402
Certificate Information: 8230-8232 N MAMMOTH AVE 91402
- Application / Permit
- 25016-20000-20558
- Plan Check / Job No.
- B25VN18681
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Convert attached garage to new ADU per GC 66323(a)(1). All work per WFPP
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Current Status
- CofO Issued on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | NAREG ATARIAN |
| Corrections Issued | 7/3/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/16/2025 | NAREG ATARIAN |
| Issued | 7/17/2025 | APPLICANT |
| CofO in Progress | 3/27/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/21/2026 | RUBEN SALAS |
| CofO Issued | 4/21/2026 | RUBEN SALAS |
| Permit Finaled | 4/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/7/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/7/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/10/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 10/10/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/7/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/7/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 11/7/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 11/7/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 11/7/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Rough | 11/13/2025 | Corrections Issued | DAVID MATSON |
| Gas Test | 11/13/2025 | Approved | DAVID MATSON |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 11/19/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 11/19/2025 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 11/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 11/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/24/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/24/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/24/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/1/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 12/1/2025 | Approved | MATTHEW NELSON |
| Insulation | 12/1/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/11/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 3/6/2026 | No Access for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/6/2026 | No Access for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/6/2026 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 3/13/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/13/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/13/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 3/26/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 3/26/2026 | Approved | OGANES TARAKHCHYAN |