569 N IRVING BLVD 90004
Certificate Information: 569 N IRVING BLVD 90004
- Application / Permit
- 25016-20000-20440
- Plan Check / Job No.
- B25VN18515
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) (18'-4" x 18'-3") DETACHED GARAGE INTO AN ADU PER GC66323 (a)(1). NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/21/2025
- Issuing Office
- Valley
- Current Status
- Issued on 11/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 7/5/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 7/8/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 7/21/2025 | APPLICANT |
| Applicant returned to address corrections | 11/3/2025 | EDWARD MEHRABIAN |
| Applicant returned to address corrections | 11/13/2025 | EDWARD MEHRABIAN |
| Plan Check Approved | 11/17/2025 | EDWARD MEHRABIAN |
| Issued | 11/21/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 7/31/2025 | ROSALINDA MEZA |
| ZI | Cleared | 7/31/2025 | ROSALINDA MEZA |
| Address approval | Cleared | 8/11/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 8/11/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/18/2025 | DERRICK MAGEE |
| Construction within easement | Cleared | 10/23/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Oasis Builders Inc; Lic. No.: 1055132-B | 11500 WEST OLYMPIC BLVD STE 400 LOS ANGELES, CA 90064 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/22/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 12/22/2025 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 2/6/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/13/2026 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/16/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/18/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/21/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 5/21/2026 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/2/2026 | Approved Pending GreenApproval | JOSH MEISTER |
| Green Building Rough | 6/2/2026 | Not Ready for Inspection | JOSH MEISTER |