651 W 60TH ST 90044
Certificate Information: 651 W 60TH ST 90044
- Application / Permit
- 25016-20000-20368
- Plan Check / Job No.
- B25VN18424
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: interior remodel of a bathroom adding a new toilet room ,new laundry closet. demolishing one interior load bering wall. new exterior sliding door and entrance steps at rear bedroom.
- Permit Issued
- Issued on 7/21/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/4/2025
Permit Application Status History
| Submitted | 6/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2025 | NGHI SU |
| Corrections Issued | 7/2/2025 | NGHI SU |
| Plan Check Approved | 7/18/2025 | NGHI SU |
| Issued | 7/21/2025 | APPLICANT |
| Permit Finaled | 12/4/2025 | BARRY HACHE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/3/2025 | MICHAEL BROWN |
| CPC | Cleared | 7/8/2025 | BRENNEN OBETO |
| Community Plan Implem. Overlay | Cleared | 7/15/2025 | MANERI ROMAN |
Contact Information
| Contractor | Aramax Construction Services; Lic. No.: 1069106-B | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 7/31/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 8/4/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 8/13/2025 | Approved | BARRY HACHE |
| Insulation | 8/14/2025 | Partial Approval | RONNIE MEDINA |
| Shower Pan | 8/15/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 8/18/2025 | Corrections Issued | STUART CHAPMAN |
| Shower Pan | 8/18/2025 | Approved | STUART CHAPMAN |
| HVAC-Rough | 8/20/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 8/22/2025 | Approved | RONNIE MEDINA |
| HVAC-Rough | 8/26/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/26/2025 | Approved | ANTHONY RAMOS |
| Final | 10/31/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 11/5/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 11/5/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 11/12/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 11/12/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 11/12/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 11/17/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Not Ready | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | ANTHONY RAMOS |
| ELECTRICAL-Final | 11/26/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 11/26/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | BARRY HACHE |
| Final | 12/4/2025 | Permit Finaled | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Approved | BARRY HACHE |