19312 W ROMAR ST 91324
Certificate Information: 19312 W ROMAR ST 91324
- Application / Permit
- 25016-20000-20234
- Plan Check / Job No.
- B25VN18269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE AND CONVERT A PORTION OF THE (E) CARPORT INTO SINGLE FAMILY DWELLING LIVING SPACE. ENCLOSE AND CONVERT (E) PATIO COVER INTO SINGLE FAMILY DWELLING LIVING SPACE. INTERIOR REMODEL TO THE (E) KITCHEN.
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- Issued on 7/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/1/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/16/2025 | GIOVANNY CHAVEZ |
| Issued | 7/31/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/4/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 9/4/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 9/4/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 9/5/2025 | Corrections Issued | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/5/2026 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 4/9/2026 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/17/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 4/17/2026 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 4/17/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/27/2026 | Not Ready for Inspection | ROBERT GOLD |
| Final | 5/27/2026 | Corrections Issued | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 5/27/2026 | Not Ready for Inspection | ROBERT GOLD |