20821-20823 W STAGG ST 91306

Certificate Information: 20821-20823 W STAGG ST 91306

Application / Permit
25016-20000-19820
Plan Check / Job No.
B25VN17895
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Conversion (E) attached garage to ADU per GCS 6582.2(e)(1)(A).
Permit Issued
Issued on 7/2/2025
Issuing Office
Current Status
CofO Issued on 1/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 TSE MING HUANG
Corrections Issued 6/27/2025 TSE MING HUANG
Plan Check Approved 7/1/2025 TSE MING HUANG
Issued 7/2/2025 APPLICANT
CofO in Progress 10/15/2025 ALEXANDER HANDY
Permit Finaled 1/7/2026 MICHAEL PELHAM
CofO Issued 1/7/2026 MICHAEL PELHAM
Permit Finaled 1/7/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 6/30/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/30/2025 LEE GUILBEAUX
Sewer availability Cleared 6/30/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/30/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 7/17/2025 Corrections Issued ALEXANDER HANDY
Deputy Drilled-In Anchors 7/18/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 8/8/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 8/8/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 8/8/2025 Approved ALEXANDER HANDY
ELECTRICAL-Rough 8/15/2025 Approved ALEXANDER HANDY
Insulation 8/15/2025 Partial Approval ALEXANDER HANDY
Interior/Exterior Lathing 8/15/2025 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Corrections Issued JUAN ALVARADO
HVAC-Rough 8/21/2025 Approved JUAN ALVARADO
Insulation 8/21/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 8/25/2025 Approved KRISTEN CAUSEY
Green Building Rough 8/25/2025 Approved KRISTEN CAUSEY
Insulation 8/25/2025 Approved KRISTEN CAUSEY
Drywall Nailing 8/28/2025 Approved KRISTEN CAUSEY
Green Building Rough 8/28/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/28/2025 Approved KRISTEN CAUSEY
Shower Pan 8/28/2025 Approved KRISTEN CAUSEY
Final 10/8/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 10/8/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready ALEXANDER HANDY
Smoke Detectors 10/8/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 10/14/2025 Approved ALEXANDER HANDY
Final 10/14/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 10/14/2025 Approved ALEXANDER HANDY
PLUMBING-Final 10/14/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved ALEXANDER HANDY
Service/Power Release 10/14/2025 Approved ALEXANDER HANDY