9040-9040 1/2 N LEDGE AVE 91352

Certificate Information: 9040-9040 1/2 N LEDGE AVE 91352

Application / Permit
25016-20000-19736
Plan Check / Job No.
B25VN17795
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT (E) CARPORT IN SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333
Permit Issued
Issued on 10/27/2025
Issuing Office
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/27/2025 DANIEL YIP
Corrections Issued 6/28/2025 DANIEL YIP
Applicant returned to address corrections 9/12/2025 DANIEL YIP
Plan Check Approved 10/23/2025 DANIEL YIP
Issued 10/27/2025 APPLICANT
CofO in Progress 5/9/2026 DAVID ANDERSON
Permit Finaled 6/3/2026 RUBEN SALAS
Permit Finaled 6/3/2026 RUBEN SALAS
CofO Issued 6/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/18/2025 RYAN CASTRO
Sewer availability Cleared 7/18/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/25/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 10/23/2025 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/2/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/8/2025 Approved DAVID ANDERSON
PLUMBING-Rough 12/22/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 1/22/2026 Approved DAVID ANDERSON
Gas Test 1/22/2026 Approved DAVID ANDERSON
HVAC-Rough 1/22/2026 Approved DAVID ANDERSON
PLUMBING-Rough 1/22/2026 Approved DAVID ANDERSON
Sewer 1/22/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/3/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved DAVID ANDERSON
Insulation 2/12/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/12/2026 Partial Approval DAVID ANDERSON
Drywall Nailing 2/25/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/25/2026 Approved DAVID ANDERSON
Shower Pan 2/25/2026 Approved DAVID ANDERSON
Final 4/17/2026 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/17/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 4/17/2026 Not Ready for Inspection DAVID ANDERSON
Final 4/28/2026 OK to Issue CofO DAVID ANDERSON
Smoke Detectors 4/28/2026 Approved DAVID ANDERSON