22623-22625 W CASS AVE 91364
Certificate Information: 22623-22625 W CASS AVE 91364
- Application / Permit
- 25016-20000-19484
- Plan Check / Job No.
- B25VN17510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND PORTION TO LAUNDRY ROOM. ALL WORK PER WFPP
- Permit Issued
- Issued on 9/9/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/27/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/27/2025 | APPLICANT |
| Plan Check Approved | 9/9/2025 | GIOVANNY CHAVEZ |
| Issued | 9/9/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/29/2025 | JACQUELINE TORRES |
| Construction near power lines | Cleared | 8/15/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 8/15/2025 | GEVORK KARAPETYAN |
| Grading Pre-Inspection | Cleared | 8/25/2025 | CHARLES POWELL |
| Address approval | Cleared | 8/29/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/29/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/29/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/20/2026 | Partial Approval | SEAN WIRCH |
| Sewer | 1/20/2026 | Approved | SEAN WIRCH |
| Deputy Drilled-In Anchors | 1/22/2026 | Conditional Approval | JOHN HAYES |
| Special/Order Compliance | 1/26/2026 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/29/2026 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/10/2026 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 2/10/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/2/2026 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 3/2/2026 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/2/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/12/2026 | Approved | JOHN HAYES |
| Green Building Rough | 3/12/2026 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/12/2026 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | JOHN HAYES |
| Insulation | 3/19/2026 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/19/2026 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 3/26/2026 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 3/26/2026 | Approved | HENRY KIM |
| Drywall Nailing | 4/1/2026 | Partial Approval | HENRY KIM |
| HVAC-Final | 4/1/2026 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 4/9/2026 | Partial Approval | JOHN HAYES |