6406 N DENSMORE AVE 91406

Certificate Information: 6406 N DENSMORE AVE 91406

Application / Permit
25016-20000-19339
Plan Check / Job No.
B25VN17342
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
Permit Issued
Issued on 7/22/2025
Issuing Office
Current Status
CofO Issued on 10/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/23/2025 OMAR GARNICA
Corrections Issued 6/24/2025 OMAR GARNICA
Applicant returned to address corrections 7/3/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/10/2025 SERGIO MUNIZ
Plan Check Approved 7/21/2025 OMAR GARNICA
Issued 7/22/2025 APPLICANT
CofO in Progress 10/29/2025 GAREN HAYRAPETYAN
Permit Finaled 10/31/2025 RUBEN SALAS
CofO Issued 10/31/2025 RUBEN SALAS
Permit Finaled 10/31/2025 RUBEN SALAS

Permit Application Clearance Information

Construction within easement Cleared 6/26/2025 WALTER RAMIREZ
Address approval Cleared 7/1/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/1/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/1/2025 SAFA JAVANMARDI

Contact Information

Contractor Lee Richard C C; Lic. No.: 292360-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/23/2025 Conditional Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 7/23/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 7/23/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/23/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/25/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 7/25/2025 Partial Approval GAREN HAYRAPETYAN
Sewer 7/25/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 7/25/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 7/28/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 7/28/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 7/28/2025 Corrections Issued KEVIN BERBERYAN
Wood Frame 7/28/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 7/29/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 7/29/2025 Approved SALVADOR MARTINEZ
Insulation 7/31/2025 Corrections Issued GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/31/2025 Partial Approval GAREN HAYRAPETYAN
Wood Frame 7/31/2025 Approved GAREN HAYRAPETYAN
Insulation 8/1/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 8/4/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 10/10/2025 Approved GAREN HAYRAPETYAN
Final 10/10/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 10/10/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 10/10/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 10/10/2025 Approved GAREN HAYRAPETYAN
MERV13>=Rough 10/10/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 10/10/2025 Approved GAREN HAYRAPETYAN
Final 10/29/2025 OK to Issue CofO GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved GAREN HAYRAPETYAN