22117 W RUNNYMEDE ST 91303

Certificate Information: 22117 W RUNNYMEDE ST 91303

Application / Permit
25016-20000-19012
Plan Check / Job No.
B25VN17066
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE AND (E) WORKSHOP TO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
Permit Issued
Issued on 7/24/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 JESSE ARELLANO
Corrections Issued 6/21/2025 JESSE ARELLANO
Building Plans Picked Up 6/26/2025 APPLICANT
Plan Check Approved 7/24/2025 YAQUB MIRZA
Issued 7/24/2025 APPLICANT
CofO in Progress 4/16/2026 JEFFREY HARTLINE
Permit Finaled 4/16/2026 JOHN JANSON
CofO Issued 4/16/2026 JOHN JANSON
Permit Finaled 4/16/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/11/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/11/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/14/2025 SAFA JAVANMARDI
Construction near power lines Cleared 7/23/2025 GEVORK KARAPETYAN
Construction within easement Cleared 7/23/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/30/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/23/2025 Partial Approval JEFFREY HARTLINE
Underground Mechanical 9/23/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 10/8/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/23/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Rough 10/23/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 12/16/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 12/16/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Partial Approval JEFFREY HARTLINE
Green Building Rough 12/16/2025 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 12/16/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/16/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 1/16/2026 Approved CHRIS CHRISTENSEN
Green Building Rough 1/16/2026 Approved CHRIS CHRISTENSEN
HVAC-Rough 1/16/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/16/2026 Partial Approval CHRIS CHRISTENSEN
Insulation 1/21/2026 Approved CHRIS CHRISTENSEN
Drywall Nailing 3/2/2026 Approved CHRIS CHRISTENSEN
Shower Pan 3/2/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/6/2026 Approved CHRIS CHRISTENSEN
Final 4/9/2026 Corrections Issued JEFFREY HARTLINE
Green Building Final 4/9/2026 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 4/9/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Final 4/15/2026 Approved JEFFREY HARTLINE
Final 4/15/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 4/15/2026 Approved JEFFREY HARTLINE
HVAC-Final 4/15/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 4/15/2026 Approved JEFFREY HARTLINE