7846-7850 W KYLE ST 91040

Certificate Information: 7846-7850 W KYLE ST 91040

Application / Permit
25016-20000-18926
Plan Check / Job No.
B25VN16977
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage to new JADU per GC 66323(a)(1) and 663333. All work per WFPP
Permit Issued
Issued on 7/24/2025
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 NAREG ATARIAN
Corrections Issued 6/18/2025 NAREG ATARIAN
Building Plans Picked Up 7/21/2025 APPLICANT
Plan Check Approved 7/24/2025 YAQUB MIRZA
Issued 7/24/2025 APPLICANT
CofO in Progress 10/28/2025 DAVID ANDERSON
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/8/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/8/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/9/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/31/2025 Partial Inspection WILLIAM WREN
Excavation/Setback/Form/Re-Bar 8/6/2025 Approved WILLIAM WREN
Footing/Foundation/Slab 8/6/2025 Approved WILLIAM WREN
PLUMBING-Rough 8/11/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 8/15/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/20/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/20/2025 Approved WILLIAM WREN
Green Building Rough 8/20/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 8/29/2025 Partial Approval WILLIAM WREN
Shower Pan 8/29/2025 Approved WILLIAM WREN
HVAC-Rough 9/2/2025 Partial Approval WAYNE REGESTER
Insulation 9/2/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 9/4/2025 Approved WILLIAM WREN
Drywall Nailing 9/10/2025 Approved STUART CHAPMAN
Final 10/23/2025 Corrections Issued MATTHEW NELSON
Green Building Final 10/23/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/23/2025 Approved MATTHEW NELSON
Final 10/27/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 10/27/2025 Approved DAVID ANDERSON