7846-7850 W KYLE ST 91040
Certificate Information: 7846-7850 W KYLE ST 91040
- Application / Permit
- 25016-20000-18926
- Plan Check / Job No.
- B25VN16977
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage to new JADU per GC 66323(a)(1) and 663333. All work per WFPP
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | NAREG ATARIAN |
| Corrections Issued | 6/18/2025 | NAREG ATARIAN |
| Building Plans Picked Up | 7/21/2025 | APPLICANT |
| Plan Check Approved | 7/24/2025 | YAQUB MIRZA |
| Issued | 7/24/2025 | APPLICANT |
| CofO in Progress | 10/28/2025 | DAVID ANDERSON |
| CofO Issued | 12/18/2025 | RUBEN SALAS |
| Permit Finaled | 12/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/8/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2025 | Partial Inspection | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 8/6/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/11/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 8/15/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 8/20/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | WILLIAM WREN |
| Shower Pan | 8/29/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/2/2025 | Partial Approval | WAYNE REGESTER |
| Insulation | 9/2/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 9/4/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/10/2025 | Approved | STUART CHAPMAN |
| Final | 10/23/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/23/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 10/23/2025 | Approved | MATTHEW NELSON |
| Final | 10/27/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 10/27/2025 | Approved | DAVID ANDERSON |