622 W 52ND ST 90037

Certificate Information: 622 W 52ND ST 90037

Application / Permit
25016-20000-18816
Plan Check / Job No.
B25VN16834
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (e) detached garage to ADU per GC 66323(a)(1). All work done per WFPP
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO Issued on 12/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2025 APPLICANT
Assigned to Plan Check Engineer 6/24/2025 DAVID CASTILLO
Corrections Issued 6/24/2025 DAVID CASTILLO
Applicant returned to address corrections 7/18/2025 REZA HAGHIGHAT
Plan Check Approved 8/16/2025 REZA HAGHIGHAT
Issued 8/18/2025 APPLICANT
CofO in Progress 12/26/2025 MICHAEL LEWIS
Permit Finaled 12/28/2025 DEROLD HAUFF
CofO Issued 12/28/2025 DEROLD HAUFF
Permit Finaled 12/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/12/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/12/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 8/12/2025 CELINA MORENO
Sewer availability Cleared 8/12/2025 CELINA MORENO
Community Plan Implem. Overlay Cleared 8/14/2025 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL BARAJAS, (213) 202-3211 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2025 No Access for Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/9/2025 Corrections Issued MICHAEL LEWIS
Pre-Inspection 9/9/2025 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 10/1/2025 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 10/7/2025 Partial Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/24/2025 Not Ready for Inspection MICHAEL LEWIS
Footing/Foundation/Slab 10/24/2025 Not Ready for Inspection MICHAEL LEWIS
Deputy Drilled-In Anchors 10/27/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/27/2025 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 11/4/2025 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 11/17/2025 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/17/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 11/17/2025 Approved MICHAEL LEWIS
HVAC-Rough 11/17/2025 Approved MICHAEL LEWIS
PLUMBING-Rough 11/17/2025 Approved MICHAEL LEWIS
Sewer 11/25/2025 Approved MICHAEL LEWIS
Underground Mechanical 11/25/2025 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Approved MICHAEL LEWIS
Insulation 12/3/2025 Approved MICHAEL LEWIS
Underground Mechanical 12/3/2025 Approved MICHAEL LEWIS
Drywall Nailing 12/5/2025 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/5/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/19/2025 Approved MICHAEL LEWIS
Final 12/19/2025 Corrections Issued MICHAEL LEWIS
Green Building Final 12/19/2025 Approved MICHAEL LEWIS
Green Building Rough 12/19/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 12/19/2025 Corrections Issued MICHAEL LEWIS
Final 12/24/2025 OK to Issue CofO MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 12/24/2025 Approved MICHAEL LEWIS