6326 N CAMELLIA AVE 91606

Certificate Information: 6326 N CAMELLIA AVE 91606

Application / Permit
25016-20000-18775
Plan Check / Job No.
B25VN16804
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18'3"X18'4" GARAGE TO AN SB-9 SINGLE FAMILY DWELLING UNIT [ALL WORK PER WFPP] (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT)
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
Issued on 9/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/11/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 MARVEL DELACRUZ
Corrections Issued 6/27/2025 MARVEL DELACRUZ
Quality Review Completed 7/3/2025 JASON HEALEY
Building Plans Picked Up 7/14/2025 APPLICANT
Applicant returned to address corrections 9/22/2025 MARVEL DELACRUZ
Plan Check Approved 9/22/2025 MARVEL DELACRUZ
Issued 9/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/3/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/7/2025 MICHAEL BROWN
Sewer availability Cleared 7/7/2025 MICHAEL BROWN
Senate Bill 9 Cleared 7/15/2025 ALEX VELA

Contact Information

Contractor We The People Construction Inc; Lic. No.: 1076924-B 5352 LAUREL CANYON BLVD # 200      VALLEY VILLAGE, CA 91607

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/15/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/6/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/31/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 12/31/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 12/31/2025 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/7/2026 Not Ready for Inspection JOSE AVILA
Pre-Inspection 1/26/2026 Partial Inspection JOSE AVILA
Pre-Inspection 2/18/2026 Partial Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/21/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/30/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/30/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/30/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/30/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/30/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 5/8/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 6/22/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 6/30/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/30/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/2/2026 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 7/2/2026 Approved JAVIER RAMOS JR
Drywall Nailing 7/13/2026 Approved ROBERTO PALACIOS-LOPEZ