6738 N CEDROS AVE 91405
Certificate Information: 6738 N CEDROS AVE 91405
- Application / Permit
- 25016-20000-18655
- Plan Check / Job No.
- B25VN16659
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan - GARAGE CONVERSION TO ADU PER STATE LAW Conversion of an existing unpermitted structure built prior to Jan 1 2020 to an Accessory Dwelling Unit.
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Issued on 8/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 6/14/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 8/4/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/11/2025 | NEHEMIAS RAMOS |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/18/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/1/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOAQUIN GREENOUGH, (818) 374-1180 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/24/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Pre-Inspection | 10/24/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 10/24/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/18/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 12/18/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/18/2025 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 12/18/2025 | Approved | JOAQUIN GREENOUGH |
| Insulation | 12/18/2025 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/18/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/13/2026 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/13/2026 | Corrections Issued | JOSE AVILA |
| Final | 2/13/2026 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Ready | JOSE AVILA |