19851 W REDWING ST 91364
Certificate Information: 19851 W REDWING ST 91364
- Application / Permit
- 25016-20000-18537
- Plan Check / Job No.
- B25VN16494
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 18'X48' RECREATION ROOM TO DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1) ALL WORK PER WFPP
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Current Status
- CofO in Progress on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/18/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 6/20/2025 | APPLICANT |
| Applicant returned to address corrections | 8/4/2025 | AUNG SOE |
| Plan Check Approved | 8/25/2025 | DANIEL SMILEY |
| Issued | 8/25/2025 | APPLICANT |
| CofO in Progress | 3/17/2026 | JOHN HAYES |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/20/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 7/30/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/16/2025 | Partial Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/3/2025 | Partial Inspection | JOHN HAYES |
| MERV13>=Rough | 10/3/2025 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 10/15/2025 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 10/23/2025 | Approved | JOHN HAYES |
| Pre-Inspection | 10/23/2025 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/3/2025 | Partial Approval | JOHN HAYES |
| MERV13>=Rough | 11/3/2025 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 11/3/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/18/2025 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 11/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 12/17/2025 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/17/2025 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 12/17/2025 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/17/2025 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| Grounding or Bonding | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/19/2025 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/9/2026 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 1/9/2026 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/9/2026 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/9/2026 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 1/15/2026 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Not Ready | HENRY KIM |
| Special/Order Compliance | 1/15/2026 | Approved | ROBERT GOLD |
| Special/Order Compliance | 1/15/2026 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 1/15/2026 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 1/26/2026 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/2/2026 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/2/2026 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 2/2/2026 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 2/2/2026 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/2/2026 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/11/2026 | Approved | JOHN HAYES |
| Final | 3/11/2026 | OK to Issue CofO | JOHN HAYES |
| MERV13>=Final | 3/11/2026 | Approved | JOHN HAYES |
| MERV13>=Rough | 3/11/2026 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 3/11/2026 | Approved | JOHN HAYES |
| Smoke Detectors | 3/11/2026 | Approved | JOHN HAYES |