6628 N TROOST AVE 91606
Certificate Information: 6628 N TROOST AVE 91606
- Application / Permit
- 25016-20000-17941
- Plan Check / Job No.
- B25VN15827
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TO REMOVE (E) ENCLOSED PATIO COVER AND CREATE NEW ADDITION TO THE (E) SINGLE FAMILY DWELLING. NEW CALIFORNIA ROOF FRAMING.
- Permit Issued
- Issued on 8/21/2025
- Issuing Office
- Current Status
- Issued on 8/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/7/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 7/24/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 8/13/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/20/2025 | GIOVANNY CHAVEZ |
| Issued | 8/21/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/24/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 8/19/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mccann,, Maxwell James; Lic. No.: C77614 | 1541 W AMERIGE AVE FULLERTON, CA 92833 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 6/8/2026 |
| ELECTRICAL-Rough | 6/8/2026 |
| HVAC-Rough | 6/8/2026 |
| BUILDING-Rough-Frame | 6/10/2026 |
| Green Building Rough | 6/10/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/24/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 9/24/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/26/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/13/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/13/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/24/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/31/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |