15820 W HAYNES ST 91406

Certificate Information: 15820 W HAYNES ST 91406

Application / Permit
25016-20000-17843
Plan Check / Job No.
B25VN15730
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(A)(2) ALL WORK PER WFPP
Permit Issued
Issued on 6/16/2025
Issuing Office
Current Status
CofO Issued on 1/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 JEROME MAGAT PALMA
Corrections Issued 6/7/2025 JEROME MAGAT PALMA
Building Plans Picked Up 6/11/2025 APPLICANT
Plan Check Approved 6/16/2025 SEWADA ZADOORAN MILAGARDI
Plan Check Approved 6/16/2025 SEWADA ZADOORAN MILAGARDI
Issued 6/16/2025 APPLICANT
CofO in Progress 11/25/2025 GAREN HAYRAPETYAN
Permit Finaled 1/7/2026 RUBEN SALAS
CofO Issued 1/7/2026 RUBEN SALAS
Permit Finaled 1/7/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/9/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/9/2025 LEE GUILBEAUX
Sewer availability Cleared 6/9/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/9/2025 LEE GUILBEAUX
Public Works-Sewers Cleared 6/9/2025 LEE GUILBEAUX
Construction within easement Cleared 6/13/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/17/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/17/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 7/23/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 7/28/2025 Partial Approval SALVADOR MARTINEZ
Sewer 7/28/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/28/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 7/30/2025 Partial Approval SALVADOR MARTINEZ
Sewer 8/4/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 8/4/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/7/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 8/7/2025 Approved KEVIN BERBERYAN
Green Building Rough 8/7/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 8/7/2025 Approved KEVIN BERBERYAN
MERV13>=Rough 8/7/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 8/11/2025 Approved KEVIN BERBERYAN
Underground Mechanical 8/11/2025 Corrections Issued KEVIN BERBERYAN
Insulation 8/13/2025 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 8/13/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 8/19/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 8/19/2025 Partial Approval SALVADOR MARTINEZ
Special/Order Compliance 8/19/2025 Corrections Issued SALVADOR MARTINEZ
Insulation 8/21/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 8/21/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 9/4/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 11/13/2025 Approved GAREN HAYRAPETYAN
Final 11/13/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 11/13/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/13/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 11/13/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 11/13/2025 Approved GAREN HAYRAPETYAN
Final 11/25/2025 OK to Issue CofO GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved GAREN HAYRAPETYAN