6698 N BLUCHER AVE 91406

Certificate Information: 6698 N BLUCHER AVE 91406

Application / Permit
25016-20000-17840
Plan Check / Job No.
B25VN15724
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 7/18/2025
Issuing Office
Valley
Current Status
CofO in Progress on 5/28/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 JEROME MAGAT PALMA
Corrections Issued 6/6/2025 JEROME MAGAT PALMA
Building Plans Picked Up 6/12/2025 APPLICANT
Plan Check Approved 7/9/2025 ISIS ARGUETA
Issued 7/18/2025 APPLICANT
CofO in Progress 5/28/2026 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 6/21/2025 BRYAN GODINEZ
Sewer availability Cleared 6/21/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/26/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/15/2025 Approved RYAN SALAZAR
PLUMBING-Rough 8/19/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/30/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/30/2025 Approved RYAN SALAZAR
Green Building Rough 10/30/2025 Approved RYAN SALAZAR
MERV13>=Rough 10/30/2025 Approved RYAN SALAZAR
PLUMBING-Rough 10/30/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/7/2025 Conditional Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved JACK KARGODORIAN
Insulation 11/7/2025 Partial Approval JACK KARGODORIAN
Wood Frame 11/7/2025 Approved JACK KARGODORIAN
Drywall Nailing 11/24/2025 Approved RYAN SALAZAR
HVAC-Rough 11/24/2025 Approved RYAN SALAZAR
Sewer 12/5/2025 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 12/5/2025 Corrections Issued JACK KARGODORIAN
Sewer 12/10/2025 Approved CRAIG DAVIS
Underground Mechanical 12/10/2025 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 2/6/2026 Partial Approval JACK KARGODORIAN
Underground Mechanical 2/6/2026 Partial Approval JACK KARGODORIAN
Shower Pan 2/24/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 3/4/2026 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 4/6/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 5/8/2026 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 5/18/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 5/18/2026 Corrections Issued VINCENT HANLEY
Final 5/18/2026 Corrections Issued VINCENT HANLEY
Green Building Final 5/18/2026 Approved VINCENT HANLEY
HVAC-Final 5/18/2026 Approved VINCENT HANLEY
MERV13>=Final 5/18/2026 Approved VINCENT HANLEY
PLUMBING-Final 5/18/2026 Approved VINCENT HANLEY
Service/Power Release 5/18/2026 Approved VINCENT HANLEY
Smoke Detectors 5/18/2026 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 5/26/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 5/26/2026 Approved VINCENT HANLEY
Final 5/26/2026 OK to Issue CofO VINCENT HANLEY