7404-7406 N LEMP AVE 91605

Certificate Information: 7404-7406 N LEMP AVE 91605

Application / Permit
25016-20000-17773
Plan Check / Job No.
B25VN15653
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC66323(a)(1) and 66333. REMODEL (E) SFD. WORK PER WFPP.
Permit Issued
Issued on 6/20/2025
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 JESSE ARELLANO
Corrections Issued 6/7/2025 JESSE ARELLANO
Building Plans Picked Up 6/9/2025 APPLICANT
Plan Check Approved 6/20/2025 OMAR GARNICA
Issued 6/20/2025 APPLICANT
CofO in Progress 5/21/2026 ROBERTO PALACIOS-LOPEZ
CofO Issued 6/17/2026 RUBEN SALAS
Permit Finaled 6/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/13/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/13/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/13/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/27/2025 Partial Approval JOSE AVILA
Sewer 8/27/2025 Approved JOSE AVILA
Deputy Drilled-In Anchors 9/10/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/10/2025 Corrections Issued JOSE AVILA
Underground Mechanical 9/19/2025 Approved JOSE AVILA
PLUMBING-Rough 9/30/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 10/9/2025 Approved JOSE AVILA
HVAC-Rough 10/9/2025 Approved JOSE AVILA
PLUMBING-Rough 10/9/2025 Approved JOSE AVILA
Insulation 10/22/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 11/20/2025 Approved JOSE AVILA
HVAC-Rough 11/20/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/20/2025 Approved JOSE AVILA
Shower Pan 11/20/2025 Partial Approval JOSE AVILA
Interior/Exterior Lathing 12/3/2025 Approved LOUIS ESCOTO
Shower Pan 12/3/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 5/5/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 5/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 5/5/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/5/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/5/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 5/20/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 5/20/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 5/21/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ