7404-7406 N LEMP AVE 91605
Certificate Information: 7404-7406 N LEMP AVE 91605
- Application / Permit
- 25016-20000-17773
- Plan Check / Job No.
- B25VN15653
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC66323(a)(1) and 66333. REMODEL (E) SFD. WORK PER WFPP.
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- CofO Issued on 6/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | JESSE ARELLANO |
| Corrections Issued | 6/7/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 6/9/2025 | APPLICANT |
| Plan Check Approved | 6/20/2025 | OMAR GARNICA |
| Issued | 6/20/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 6/17/2026 | RUBEN SALAS |
| Permit Finaled | 6/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/13/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/27/2025 | Partial Approval | JOSE AVILA |
| Sewer | 8/27/2025 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 9/10/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/10/2025 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 9/19/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/30/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/9/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 10/9/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/9/2025 | Approved | JOSE AVILA |
| Insulation | 10/22/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 11/20/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/20/2025 | Approved | JOSE AVILA |
| Shower Pan | 11/20/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 12/3/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/3/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/20/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 5/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/21/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |