10834 1/2 N ODELL AVE 91040
Certificate Information: 10834 1/2 N ODELL AVE 91040
- Application / Permit
- 25016-20000-17630
- Plan Check / Job No.
- B25VN15473
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert (E) Detached Garage to Accessory Dwelling Unit with storage room addtion per engineer design (State ADU Types, GC 66323(a)(2))
- Permit Issued
- Issued on 8/2/2025
- Issuing Office
- Current Status
- CofO Issued on 6/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | NGHI SU |
| Corrections Issued | 6/4/2025 | NGHI SU |
| Applicant returned to address corrections | 6/24/2025 | AUNG SOE |
| Applicant returned to address corrections | 7/29/2025 | NGHI SU |
| Applicant returned to address corrections | 7/30/2025 | AUNG SOE |
| Plan Check Approved | 7/30/2025 | AUNG SOE |
| Issued | 8/2/2025 | APPLICANT |
| CofO in Progress | 4/21/2026 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
| CofO Issued | 6/9/2026 | RUBEN SALAS |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 6/18/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/18/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 6/20/2025 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2025 | MICHAEL BROWN |
Contact Information
| Architect | Yahchouchi,, Nadim Francis; Lic. No.: C39301 | 19621 BABINGTON ST SANTA CLARITA, CA 91351 |
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/26/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 8/26/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 8/26/2025 | No Access for Inspection | WILLIAM WREN |
| Green Building Final | 8/26/2025 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 8/26/2025 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Inspection | 9/12/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/18/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 9/23/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 10/22/2025 | Corrections Issued | WAYNE REGESTER |
| Deputy Drilled-In Anchors | 10/24/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/12/2025 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 12/17/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/18/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 2/6/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 3/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 3/20/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 3/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 3/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 3/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/2/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 4/20/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |