17310 W TUBA ST 91325
Certificate Information: 17310 W TUBA ST 91325
- Application / Permit
- 25016-20000-17419
- Plan Check / Job No.
- B25VN15187
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INT/EXT REMODEL TO EXISTING 1-STORY SFD W/ ATT GARAGE. REINFORCE EXISTING ROOF TRUSS PER ENGR. SEE COMMENTS.
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/18/2026
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2025 | JESSE ARELLANO |
| Corrections Issued | 6/4/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 6/6/2025 | APPLICANT |
| Applicant returned to address corrections | 6/21/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/25/2025 | HAYATO TSUCHIYA |
| Issued | 6/25/2025 | APPLICANT |
| Permit Finaled | 3/18/2026 | KEVIN BERBERYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/9/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Hillstar Construction Inc; Lic. No.: 972213-B | 22647 VENTURA BLVD #173 WOODLAND HILLS, CA 91364 |
| Engineer | Telian,, Vartan; Lic. No.: C94330 | 11776 PIERCE ST SYLMAR, CA 91342 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/10/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Steel/Welding | 7/16/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 7/18/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 7/21/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/22/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 7/22/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 7/22/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 8/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 8/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 9/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/5/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 9/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Shower Pan | 9/9/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/11/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 9/11/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/30/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 3/18/2026 | Permit Finaled | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 3/18/2026 | Approved | KEVIN BERBERYAN |