8346-8348 N SYLMAR AVE 91402
Certificate Information: 8346-8348 N SYLMAR AVE 91402
- Application / Permit
- 25016-20000-17271
- Plan Check / Job No.
- B25VN14998
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE EXISTING ATTACHED GARAGE TO A NEW JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) and 66333. WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/18/2026
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 7/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 6/3/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/6/2025 | APPLICANT |
| Plan Check Approved | 6/17/2025 | MADISON O'DELL |
| Issued | 2/18/2026 | APPLICANT |
| CofO in Progress | 7/22/2026 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/16/2026 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/17/2026 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/17/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/18/2026 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 3/20/2026 | Approved | OGANES TARAKHCHYAN |
| Sewer | 3/20/2026 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 3/26/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/3/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/23/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/5/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 5/5/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/5/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 5/5/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 5/13/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/20/2026 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/20/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/29/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/10/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/9/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/9/2026 | Approved | MICHEL ABAJAN |
| Final | 7/9/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/9/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/9/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/9/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/9/2026 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/9/2026 | Approved | MICHEL ABAJAN |
| Final | 7/21/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |