18206 W VICTORY BLVD 91335
Certificate Information: 18206 W VICTORY BLVD 91335
- Application / Permit
- 25016-20000-17072
- Plan Check / Job No.
- B25VN14778
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- eplan THIS PROJECT IS A VERIZON WIRELESS UNMANNED TELECOMMUNICATION WIRELESS FACILITY. IT WILL CONSIST OF THE FOLLOWING: NEW VERIZON WIRELESS (287 SQ. FT.) EQUIPMENT CABINETS LEASE AREA AT GROUND NEW VERIZON WIRELESS (3)(85 SQ. FT.) ANTENNAS LEASE AREA ON ROOFTOP. (255 SQ. FT. TOTAL ON ROOFTOP) (11) NEW VERIZON WIRELESS EQUIPMENT CABINETS MOUNTED TO NEW H-FRAME (1) NEW VERIZON WIRELESS GENERATOR PLUG (9) VERIZON ANTENNAS (1) NEW VERIZON WIRELESS 4'-0" MICROWAVE ANTENNA (6) NEW VERIZON WIRELESS RADIOS (3) NEW VERIZON WIRELESS RAYCAPS (1) NEW VERIZON WIRELESS GPS ANTENNA (1) NEW VERIZON WIRELESS SUB-METER
- Permit Issued
- Issued on 1/20/2026
- Issuing Office
- Current Status
- Issued on 1/20/2026
Permit Application Status History
| Submitted | 6/9/2025 | APPLICANT |
| Assigned to Zoning Architect | 6/12/2025 | AMIR NAKHLA |
| Assigned to Plan Check Engineer | 6/26/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 7/2/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/18/2025 | PRANITA SHAH |
| Plan Check Approved | 12/18/2025 | ARSALAN SHABESTARI |
| Issued | 1/20/2026 | APPLICANT |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 6/27/2025 | Rosendo Medina |
| Plan Approval | Cleared | 12/4/2025 | LESLIE PEREZ |
Contact Information
| Architect | Campagna,, Mitchell John; Lic. No.: NA20355 | , |
| Contractor | Clotworthy R L Construction Inc; Lic. No.: 803626-B | , |
| Engineer | Zalzali,, Wissam; Lic. No.: NA71655 | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/13/2026 | Conditional Approval | BRIAN KELLY |
| Structural Steel Frame | 5/7/2026 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 5/7/2026 | Partial Inspection | GREGORY POMISH |
| Structural Steel Frame | 5/14/2026 | Partial Approval | DEANDRE HOFFMAN |
| Structural Steel Frame | 5/19/2026 | Partial Approval | BRIAN KELLY |