13577 W GAGER ST 91331
Certificate Information: 13577 W GAGER ST 91331
- Application / Permit
- 25016-20000-16951
- Plan Check / Job No.
- B25VN14658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 12/9/2025
- Issuing Office
- Valley
- Current Status
- Issued on 12/9/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 5/31/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/3/2025 | APPLICANT |
| Plan Check Approved | 6/6/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 12/9/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 6/3/2025 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 6/6/2025 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyan,, Shant Yervant; Lic. No.: C93408 | 3344 LARGA AVE LOS ANGELES, CA 90039 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/13/2026 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/31/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/8/2026 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/22/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Rough | 4/22/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| MERV13>=Rough | 4/22/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| METHANE-Rough | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 4/22/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/8/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/8/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/8/2026 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 5/8/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/8/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 5/8/2026 | Approved | MICHEL ABAJAN |
| Insulation | 5/13/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 5/26/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/26/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/26/2026 | Approved | MICHEL ABAJAN |