3270 S STEWART AVE 90066

Certificate Information: 3270 S STEWART AVE 90066

Application / Permit
25016-20000-16950
Plan Check / Job No.
B25VN14653
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). ALL WORK PER WFPP.
Permit Issued
Issued on 8/7/2025
Issuing Office
Current Status
CofO Issued on 3/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/30/2025 HAYATO TSUCHIYA
Corrections Issued 6/2/2025 HAYATO TSUCHIYA
Building Plans Picked Up 6/2/2025 APPLICANT
Plan Check Approved 8/7/2025 ANGELICA MARTINEZ
Issued 8/7/2025 APPLICANT
CofO in Progress 3/13/2026 DAKOTA LOW
Permit Finaled 3/14/2026 RICHARD STEINBACH
CofO Issued 3/14/2026 RICHARD STEINBACH
Permit Finaled 3/14/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/5/2025 LANNY MERRICK
Address approval Cleared 6/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/11/2025 BIAINA HARITUNIAN

Contact Information

Contractor A P Remodeling Inc; Lic. No.: 1049032-B 5972 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2025 Corrections Issued MICHAEL ALLEN
Sewer 8/22/2025 Approved MICHAEL ALLEN
Underground Mechanical 8/22/2025 Approved MICHAEL ALLEN
Sewer 8/28/2025 Approved WILBER ROSALES
Underground Mechanical 8/28/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 9/4/2025 Not Ready for Inspection WILBER ROSALES
Insulation 9/4/2025 Not Ready for Inspection WILBER ROSALES
Interior/Exterior Lathing 9/4/2025 Not Ready for Inspection WILBER ROSALES
Shower Pan 9/4/2025 Not Ready for Inspection WILBER ROSALES
Deputy Drilled-In Anchors 9/5/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 9/9/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 9/9/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 10/2/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 10/2/2025 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Rough 10/20/2025 Approved WILBER ROSALES
HVAC-Rough 10/20/2025 Approved WILBER ROSALES
PLUMBING-Rough 10/20/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval JESUS RODRIGUEZ
Insulation 11/7/2025 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/3/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Approved WILBER ROSALES
Green Building Rough 12/3/2025 Approved WILBER ROSALES
Insulation 12/3/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 12/3/2025 Approved WILBER ROSALES
Drywall Nailing 12/9/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 12/9/2025 Approved WILBER ROSALES
Shower Pan 12/9/2025 Approved WILBER ROSALES
ELECTRICAL-Final 2/10/2026 Corrections Issued DAVID FEILER
Final 2/10/2026 Corrections Issued DAVID FEILER
HVAC-Final 2/10/2026 Corrections Issued DAVID FEILER
PLUMBING-Final 2/10/2026 Corrections Issued DAVID FEILER
Smoke Detectors 2/10/2026 Corrections Issued DAVID FEILER
ELECTRICAL-Final 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Final 2/24/2026 Not Ready for Inspection RUBEN RIVAS
Green Building Final 2/24/2026 Approved RUBEN RIVAS
HVAC-Final 2/24/2026 Partial Approval RUBEN RIVAS
PLUMBING-Final 2/24/2026 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved RUBEN RIVAS
Smoke Detectors 2/24/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Final 3/2/2026 Corrections Issued DAKOTA LOW
Final 3/2/2026 Not Ready for Inspection DAKOTA LOW
HVAC-Final 3/2/2026 Corrections Issued DAKOTA LOW
PLUMBING-Final 3/2/2026 Corrections Issued DAKOTA LOW
Smoke Detectors 3/2/2026 Partial Approval DAKOTA LOW
ELECTRICAL-Final 3/11/2026 Approved DAKOTA LOW
Final 3/11/2026 OK to Issue CofO DAKOTA LOW
Gas Test 3/11/2026 Approved DAKOTA LOW
HVAC-Final 3/11/2026 Approved DAKOTA LOW
PLUMBING-Final 3/11/2026 Approved DAKOTA LOW
Smoke Detectors 3/11/2026 Approved DAKOTA LOW
Special/Order Compliance 3/11/2026 Partial Inspection DAVID FEILER