6641-6643 N DANNYBOYAR AVE 91307

Certificate Information: 6641-6643 N DANNYBOYAR AVE 91307

Application / Permit
25016-20000-16895
Plan Check / Job No.
B25VN14579
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO A (N) 444 SF ADU PER GCS66323(a)(1), ALL WORK PER ENG.
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 LUISANGEL VALENZUELA
Corrections Issued 5/28/2025 LUISANGEL VALENZUELA
Plan Check Approved 6/17/2025 LUISANGEL VALENZUELA
Plan Check Approved 7/28/2025 LUISANGEL VALENZUELA
Issued 7/29/2025 APPLICANT
CofO in Progress 12/5/2025 TROY SANDERS
Permit Finaled 1/20/2026 JOHN JANSON
CofO Issued 1/20/2026 JOHN JANSON
Permit Finaled 1/20/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/11/2025 BIAINA HARITUNIAN

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,
Engineer Azaren,, Neil; Lic. No.: C89881 4583 NORTH AVE UNIT 6      SAN DIEGO, CA 92116

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/20/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 8/20/2025 Approved TROY SANDERS
PLUMBING-Rough 8/20/2025 Partial Approval TROY SANDERS
Sewer 8/20/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 9/15/2025 Approved TROY SANDERS
ELECTRICAL-Rough 9/15/2025 Approved TROY SANDERS
Green Building Rough 9/15/2025 Approved TROY SANDERS
HVAC-Rough 9/15/2025 Approved TROY SANDERS
PLUMBING-Rough 9/15/2025 Approved TROY SANDERS
Insulation 9/18/2025 Approved TROY SANDERS
Interior/Exterior Lathing 9/18/2025 Partial Approval TROY SANDERS
Shower Pan 9/18/2025 Approved TROY SANDERS
Drywall Nailing 9/26/2025 Approved TROY SANDERS
ELECTRICAL-Final 11/21/2025 Approved TROY SANDERS
Final 11/21/2025 Not Ready for Inspection TROY SANDERS
HVAC-Final 11/21/2025 Approved TROY SANDERS
PLUMBING-Final 11/21/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved TROY SANDERS
Service/Power Release 11/21/2025 Approved TROY SANDERS
Smoke Detectors 11/21/2025 Approved TROY SANDERS
Final 12/2/2025 Not Ready for Inspection TROY SANDERS
Final 12/4/2025 OK to Issue CofO TROY SANDERS