10415 N ORO VISTA AVE 91040
Certificate Information: 10415 N ORO VISTA AVE 91040
- Application / Permit
- 25016-20000-16791
- Plan Check / Job No.
- B25VN14422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED HOBBY SHOP AND STORAGE TO ADU PER GC66323(a)(1)
- Permit Issued
- Issued on 8/22/2025
- Issuing Office
- Current Status
- Issued on 8/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/28/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/20/2025 | ALEC MOUSAKHANIAN |
| Issued | 8/22/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/13/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/2/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/2/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/30/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/30/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/30/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Approved | DAVID ANDERSON |
| Insulation | 11/18/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 11/25/2025 | Approved | DAVID ANDERSON |
| Pre-Inspection | 11/25/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 12/12/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/17/2025 | Approved | DAVID ANDERSON |
| Gas Test | 4/28/2026 | Approved | DAVID ANDERSON |
| Underground Mechanical | 4/28/2026 | Partial Approval | DAVID ANDERSON |
| Grading Pre-Inspection | 6/9/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 6/29/2026 | Approved | DAVID ANDERSON |