10415 N ORO VISTA AVE 91040

Certificate Information: 10415 N ORO VISTA AVE 91040

Application / Permit
25016-20000-16791
Plan Check / Job No.
B25VN14422
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED HOBBY SHOP AND STORAGE TO ADU PER GC66323(a)(1)
Permit Issued
Issued on 8/22/2025
Issuing Office
Current Status
Issued on 8/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 ALEC MOUSAKHANIAN
Corrections Issued 5/28/2025 ALEC MOUSAKHANIAN
Plan Check Approved 8/20/2025 ALEC MOUSAKHANIAN
Issued 8/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/10/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 6/13/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/2/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/30/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 10/30/2025 Approved DAVID ANDERSON
HVAC-Rough 10/30/2025 Approved DAVID ANDERSON
PLUMBING-Rough 10/30/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Approved DAVID ANDERSON
Insulation 11/18/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/18/2025 Partial Approval DAVID ANDERSON
Drywall Nailing 11/25/2025 Approved DAVID ANDERSON
Pre-Inspection 11/25/2025 Approved DAVID ANDERSON
Shower Pan 12/12/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/17/2025 Approved DAVID ANDERSON
Gas Test 4/28/2026 Approved DAVID ANDERSON
Underground Mechanical 4/28/2026 Partial Approval DAVID ANDERSON
Grading Pre-Inspection 6/9/2026 Not Ready for Inspection DAVID ANDERSON
Sewer 6/29/2026 Approved DAVID ANDERSON