11145-11147 N DANUBE AVE 91344

Certificate Information: 11145-11147 N DANUBE AVE 91344

Application / Permit
25016-20000-16788
Plan Check / Job No.
B25VN14420
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND 66333.
Permit Issued
Issued on 7/23/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 ISIS ARGUETA
Corrections Issued 5/28/2025 ISIS ARGUETA
Building Plans Picked Up 5/29/2025 APPLICANT
Applicant returned to address corrections 6/16/2025 KAMYAR EMAMI
Plan Check Approved 6/20/2025 ALEC MOUSAKHANIAN
Issued 7/23/2025 APPLICANT
CofO in Progress 4/7/2026 JENNIFER RABUCHIN
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/30/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/30/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 6/6/2025 ALEXANDER HELFER

Contact Information

Contractor Dream Construction; Lic. No.: 1051776-B 13649 VANOWEN ST      VAN NUYS, CA 91405
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/25/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 9/8/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/8/2025 Partial Approval JENNIFER RABUCHIN
Sewer 9/8/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/8/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/8/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/8/2025 Approved JENNIFER RABUCHIN
MERV13>=Rough 10/8/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/8/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/3/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/3/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/16/2025 Approved CHRISTOPHER MORFIN
Green Building Rough 12/16/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 12/16/2025 Approved CHRISTOPHER MORFIN
Insulation 12/30/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 1/9/2026 Approved JENNIFER RABUCHIN
Final 3/31/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/31/2026 Approved JENNIFER RABUCHIN
MERV13>=Final 3/31/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/31/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/7/2026 Approved JENNIFER RABUCHIN
Final 4/7/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/7/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/7/2026 Approved JENNIFER RABUCHIN