7125 N RIVOL ROAD 91307
Certificate Information: 7125 N RIVOL ROAD 91307
- Application / Permit
- 25016-20000-16640
- Plan Check / Job No.
- B25VN14238
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Interior Structural Alteration to (E) SFD to remove interior partitions at kitchen and provide new ceiling beams and pad footings per Engineered design . (Area of Work: 344 sf)
- Permit Issued
- Issued on 7/25/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/16/2025
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | LUKE GONZALES |
| Corrections Issued | 5/29/2025 | LUKE GONZALES |
| Plan Check Approved | 7/2/2025 | GEORGE ALVAREZ |
| Issued | 7/25/2025 | APPLICANT |
| Permit Finaled | 12/15/2025 | JEFFREY HARTLINE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/2/2025 | GEORGE ALVAREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | JEFFREY HARTLINE |
| Deputy Steel/Welding | 8/25/2025 | Conditional Approval | HENRY KIM |
| Wood Frame | 9/18/2025 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/23/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 9/23/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/23/2025 | Approved | JEFFREY HARTLINE |
| Piling/Pier/Caisson | 9/23/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/29/2025 | Approved | SCOTT SOBEL |
| Insulation | 9/29/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/29/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 12/15/2025 | Approved | JEFFREY HARTLINE |
| Final | 12/15/2025 | Permit Finaled | JEFFREY HARTLINE |
| HVAC-Final | 12/15/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/15/2025 | Approved | JEFFREY HARTLINE |
| Smoke Detectors | 12/15/2025 | Approved | JEFFREY HARTLINE |