10139 W RIVERSIDE DR 91602
Certificate Information: 10139 W RIVERSIDE DR 91602
- Application / Permit
- 25016-20000-16554
- Plan Check / Job No.
- B25VN14130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Ice Cream Parlor
- Work Description
- eplan: CHANGE OF USE FROM EXISTING RETAIL TO TAKE-OUT RESTAURANT (ICE CREAM PARLOR) GELATO STORE
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | ZAW HAN |
| Corrections Issued | 5/24/2025 | ZAW HAN |
| Applicant returned to address corrections | 6/2/2025 | ZAW HAN |
| Applicant returned to address corrections | 7/17/2025 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/21/2025 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/26/2025 | GEORGE ALVAREZ |
| Plan Check Approved | 8/2/2025 | ZAW HAN |
| Issued | 8/7/2025 | APPLICANT |
| CofO in Progress | 10/14/2025 | DEANDRE HOFFMAN |
| Permit Finaled | 10/15/2025 | JEFFREY DURAN |
| CofO Issued | 10/15/2025 | JEFFREY DURAN |
| Permit Finaled | 10/15/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/9/2025 | ALEX VELA |
| CPC | Cleared | 6/9/2025 | ALEX VELA |
| ZA Case | Cleared | 6/9/2025 | ALEX VELA |
| Sewer availability | Cleared | 6/12/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2025 | CINDY QI |
| Supp. Use District POD/CDO/TDO | Cleared | 6/26/2025 | ADRINEH MELKONIAN |
| Food establishment approval | Cleared | 7/17/2025 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 7/24/2025 | CRYSTOL BRANDT |
Contact Information
| Contractor | Concierge Building And Development Llc; Lic. No.: 1082880-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2025 | Approved | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/19/2025 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 8/19/2025 | Approved | KENNETH ROBERTS |
| Wood Frame | 8/22/2025 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 8/27/2025 | Approved | DANIEL VARNUM |
| Final | 10/8/2025 | OK to Issue CofO | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 10/8/2025 | Approved | DEANDRE HOFFMAN |