11007-11009 N RESEDA BLVD 91326

Certificate Information: 11007-11009 N RESEDA BLVD 91326

Application / Permit
25016-20000-16469
Plan Check / Job No.
B25VN14071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 6/3/2025
Issuing Office
Valley
Current Status
CofO Corrected on 1/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 JEROME MAGAT PALMA
Corrections Issued 5/27/2025 JEROME MAGAT PALMA
Building Plans Picked Up 5/29/2025 APPLICANT
Issued 6/3/2025 APPLICANT
CofO in Progress 1/5/2026 KRISTEN CAUSEY
Re-Activate Permit 1/7/2026 JOHN JANSON
CofO Issued-Status Void 1/7/2026 JOHN JANSON
Permit Finaled-Status Void 1/7/2026 JOHN JANSON
Permit Finaled 1/7/2026 JOHN JANSON
CofO Corrected 1/7/2026 JOHN JANSON
Permit Finaled 1/7/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 5/30/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/30/2025 SAFA JAVANMARDI

Contact Information

Contractor Pavlovich Construction Co; Lic. No.: 388868-B 22817 VENTURA BLVD 1001      WOODLAND HILLS, CA 91364

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
DAVID SCANTLIN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/1/2025 Conditional Approval DAVID SCANTLIN
PLUMBING-Rough 7/9/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 7/24/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 7/24/2025 Approved DAVID SCANTLIN
Green Building Rough 7/24/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 7/24/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 7/24/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/1/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved DAVID SCANTLIN
Green Building Rough 8/1/2025 Approved DAVID SCANTLIN
HVAC-Rough 8/1/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/1/2025 Partial Approval DAVID SCANTLIN
Shower Pan 8/1/2025 Approved DAVID SCANTLIN
Insulation 8/5/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/5/2025 Approved DAVID SCANTLIN
Drywall Nailing 8/11/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 12/23/2025 Approved DAVID SCANTLIN
Final 12/23/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 12/23/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 12/23/2025 Approved DAVID SCANTLIN
PLUMBING-Final 12/23/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/23/2025 Approved DAVID SCANTLIN
Final 1/2/2026 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 1/2/2026 Approved KRISTEN CAUSEY