17999 W BORIS DR 91316
Certificate Information: 17999 W BORIS DR 91316
- Application / Permit
- 25016-20000-16241
- Plan Check / Job No.
- B25VN13869
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 2-CAR DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(1). WORK DONE PER ENGINEER DESIGN. *EXISTING GARAGE IS EQUIPED WITH FIRE SPRINKLER SYSTEM, FIRE SPRINKLER SYSTEM TO REMAIN FOR NEW ADU*
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/27/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 5/30/2025 | APPLICANT |
| Plan Check Approved | 6/16/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | JOHN KIDWELL |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/11/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 6/12/2025 | KURT CORRAL |
Contact Information
| Contractor | Sharp Builders Inc; Lic. No.: 1078848-B | 8432 SHARP AVE SUN VALLEY, CA 91352 |
| Engineer | Asprer,, Anjero; Lic. No.: C91126 | 2708 FOOTHILL BLVD. #1006 LA CRESCENTA, CA 91214 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/29/2025 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 9/29/2025 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Conditional Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/1/2025 | Conditional Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/8/2025 | Conditional Approval | JOHN KIDWELL |
| Green Building Rough | 12/8/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 12/8/2025 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/8/2025 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/11/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/30/2025 | Approved | JOHN KIDWELL |
| Final | 4/22/2026 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 4/22/2026 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Not Required | JOHN KIDWELL |
| Smoke Detectors | 4/22/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/6/2026 | Approved | JOHN KIDWELL |
| Final | 5/6/2026 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/6/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 5/6/2026 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 5/6/2026 | Approved | JOHN KIDWELL |
| Final | 6/3/2026 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 6/3/2026 | Approved | JOHN KIDWELL |