18558 W GILMORE ST 91335
Certificate Information: 18558 W GILMORE ST 91335
- Application / Permit
- 25016-20000-16196
- Plan Check / Job No.
- B25VN13850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 9/25/2025
- Issuing Office
- Current Status
- Issued on 9/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | SERGIO MUNIZ |
| Corrections Issued | 6/3/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/24/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/2/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/28/2025 | SERGIO MUNIZ |
| Plan Check Approved | 9/10/2025 | SERGIO MUNIZ |
| Issued | 9/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/9/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/10/2026 |
| Green Building Rough | 6/10/2026 |
| PLUMBING-Rough | 6/10/2026 |
| HVAC-Rough | 6/10/2026 |
| ELECTRICAL-Rough | 6/10/2026 |
Inspection Request History
| Pre-Inspection | 1/8/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Underground Mechanical | 1/8/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 1/14/2026 | Conditional Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 1/15/2026 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 1/29/2026 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 1/29/2026 | Partial Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 2/2/2026 | Corrections Issued | MORRIS JACKSON |
| Insulation | 2/2/2026 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/20/2026 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/20/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/29/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 4/29/2026 | Corrections Issued | MORRIS JACKSON |
| HVAC-Rough | 4/29/2026 | Approved | MORRIS JACKSON |
| Insulation | 4/29/2026 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 4/29/2026 | Corrections Issued | MORRIS JACKSON |