208-208 3/4 W 49TH ST 90037

Certificate Information: 208-208 3/4 W 49TH ST 90037

Application / Permit
25016-20000-16140
Plan Check / Job No.
B25VN13810
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan Legalize unpermitted Accessory Dwelling Unit per 65852.23 by converting portion(646 sq. sf.) of (E) rear unit of a Duplex to an ADU. Existing construction does not pose a threat to the public's health and safety was allowed per Government Code Section 55.852.2(d)(2).
Permit Issued
Issued on 4/22/2026
Issuing Office
Current Status
Issued on 4/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 MINA HABILI
Corrections Issued 5/24/2025 MINA HABILI
Applicant returned to address corrections 9/4/2025 MINA HABILI
Applicant returned to address corrections 10/30/2025 MINA HABILI
Applicant returned to address corrections 2/5/2026 MINA HABILI
Applicant returned to address corrections 2/28/2026 MINA HABILI
Applicant returned to address corrections 3/5/2026 SAMUEL GONZALEZ
Applicant returned to address corrections 4/1/2026 SAMUEL GONZALEZ
Plan Check Approved 4/21/2026 SAMUEL GONZALEZ
Issued 4/22/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/2/2026 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/2/2026 BIAINA HARITUNIAN
Sewer availability Cleared 1/2/2026 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/5/2026 BIAINA HARITUNIAN
Tenant Habitability Plan Cleared 1/28/2026 ARIC DEFUSCO

Contact Information

Contractor California Home Center Inc; Lic. No.: 1090079-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/11/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/20/2026 Approved ALIZAH MAYAGOITIA
Pre-Inspection 5/20/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/10/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/10/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/15/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/15/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 6/16/2026 Approved SABAS ALONSO
Green Building Rough 6/16/2026 Approved SABAS ALONSO
HVAC-Rough 6/16/2026 Approved SABAS ALONSO
PLUMBING-Rough 6/16/2026 Approved SABAS ALONSO
Underground Mechanical 6/16/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/23/2026 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 6/23/2026 Partial Approval BARRY HACHE
BUILDING-Rough-Frame 6/25/2026 Approved ALIZAH MAYAGOITIA
Insulation 6/29/2026 Approved ALEX COLIN
Drywall Nailing 7/6/2026 Corrections Issued ALEX COLIN
Drywall Nailing 7/8/2026 Approved ALEX COLIN
Interior/Exterior Lathing 7/13/2026 Approved ALEX COLIN