8944 N WHITAKER AVE 91343

Certificate Information: 8944 N WHITAKER AVE 91343

Application / Permit
25016-20000-16079
Plan Check / Job No.
B25VN13765
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED RECREATION ROOM TO NEW ACCESSORY DWELLING UNIT (734 SF) PER GC 66323(a)(1). EXISTING ATTACHED BATHROOM (69 SF) TO REMAIN (EXTERIOR ACCESS ONLY). WORK DONE PER WFPP.
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO in Progress on 3/13/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/15/2025 APPLICANT
Assigned to Plan Check Engineer 5/21/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/27/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 5/27/2025 APPLICANT
Applicant returned to address corrections 7/18/2025 MIROOSH KHACHATOORIAN
Issued 7/29/2025 APPLICANT
CofO in Progress 3/13/2026 KIRK SANDERS

Permit Application Clearance Information

Address approval Cleared 5/30/2025 SAFA JAVANMARDI
Sewer availability Cleared 5/30/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/20/2025 SAFA JAVANMARDI
Construction near power lines Cleared 7/17/2025 WALTER RAMIREZ
Hydrant and Access approval Cleared 7/29/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/4/2025 Not Ready for Inspection DAVID ANDERSON
Gas Test 8/4/2025 Approved DAVID ANDERSON
PLUMBING-Rough 8/4/2025 Approved DAVID ANDERSON
Sewer 8/4/2025 Approved DAVID ANDERSON
Wood Frame 8/4/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 8/8/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 8/8/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/14/2025 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 8/14/2025 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/18/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 8/18/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 9/22/2025 Conditional Approval GAREN HAYRAPETYAN
HVAC-Rough 9/22/2025 Approved GAREN HAYRAPETYAN
Pre-Inspection 9/22/2025 Partial Inspection GAREN HAYRAPETYAN
Shower Pan 9/22/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/22/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/22/2025 Approved GAREN HAYRAPETYAN
Insulation 10/22/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/22/2025 Partial Approval GAREN HAYRAPETYAN
Drywall Nailing 11/10/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/10/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/13/2026 Corrections Issued GAREN HAYRAPETYAN
Service/Power Release 2/13/2026 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 3/3/2026 Approved KIRK SANDERS
PLUMBING-Final 3/3/2026 Approved KIRK SANDERS
Verify Rec and Parks Fee Memo 3/3/2026 Approved KIRK SANDERS
Final 3/9/2026 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 3/9/2026 Approved KIRK SANDERS
Final 3/13/2026 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved KIRK SANDERS