4202 N HAYVENHURST AVE 91436
Certificate Information: 4202 N HAYVENHURST AVE 91436
- Application / Permit
- 25016-20000-15902
- Plan Check / Job No.
- B25VN13617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RECREATION ROOM INTO A (N) 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 66323(a)(1) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 1/30/2026
- Issuing Office
- Metro
- Current Status
- Issued on 1/30/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | ALFRED RAMIREZ |
| Corrections Issued | 6/7/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 6/12/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/17/2025 | APPLICANT |
| Applicant returned to address corrections | 8/28/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 9/19/2025 | ALFRED RAMIREZ |
| Issued | 1/30/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/29/2025 | GEVORK KARAPETYAN |
| Hydrant and Access approval | Cleared | 7/29/2025 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 8/6/2025 | ERNEST TSE |
| Address approval | Cleared | 8/7/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/7/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/7/2025 | SAFA JAVANMARDI |
| ZA Case | Cleared | 8/12/2025 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 8/28/2025 | ALFRED RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/20/2026 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 3/2/2026 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/2/2026 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/4/2026 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/13/2026 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2026 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/18/2026 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/18/2026 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 5/18/2026 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 5/18/2026 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/21/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/1/2026 | Partial Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/1/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 6/1/2026 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/8/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/8/2026 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 6/8/2026 | Approved | JOHN KIDWELL |
| Insulation | 7/10/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/10/2026 | Partial Approval | JOHN KIDWELL |