3668 E ROSEVIEW AVE 90065
Certificate Information: 3668 E ROSEVIEW AVE 90065
- Application / Permit
- 25016-20000-15493
- Plan Check / Job No.
- B25VN13314
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RECREATION ROOM BLDG INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). NO PHYSICAL CONSTRUCTIONS. SEE COMMENTS.
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/12/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/17/2025 | HAYATO TSUCHIYA |
| Issued | 6/17/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
| CofO Issued | 4/8/2026 | DEROLD HAUFF |
| Permit Finaled | 4/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/15/2025 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 6/4/2025 | ANDREA MAGANA-WITHERS |
| ZI | Cleared | 6/4/2025 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/22/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/22/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/22/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/12/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/12/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/12/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 9/30/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/10/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pre-Inspection | 10/10/2025 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 4/1/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/3/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/3/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/3/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/7/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |