8113-8115 N LURLINE AVE 91306
Certificate Information: 8113-8115 N LURLINE AVE 91306
- Application / Permit
- 25016-20000-15192
- Plan Check / Job No.
- B25VN13114
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage to 361sf ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- Issued on 6/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | SHANGQIN XIE |
| Corrections Issued | 5/23/2025 | SHANGQIN XIE |
| Plan Check Approved | 6/16/2025 | TSE MING HUANG |
| Issued | 6/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/30/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Cali Remodeling; Lic. No.: 1061730-B | , |
| Contractor | G E J Construction Inc; Lic. No.: 1061730-B | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2025 | Partial Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 9/24/2025 | Corrections Issued | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 10/7/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 10/8/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/20/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/12/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/12/2025 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/17/2025 | Partial Approval | TROY SANDERS |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 1/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 1/20/2026 | Approved | DAVID SCANTLIN |
| Insulation | 2/3/2026 | Partial Approval | DAVID FASTIGGI |
| Drywall Nailing | 2/18/2026 | Corrections Issued | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 2/26/2026 | Approved | DAVID FASTIGGI |
| Green Building Rough | 2/26/2026 | Approved | DAVID FASTIGGI |
| Drywall Nailing | 3/2/2026 | Approved | DAVID FASTIGGI |
| Interior/Exterior Lathing | 3/2/2026 | Approved | DAVID FASTIGGI |
| Interior/Exterior Lathing | 3/6/2026 | Approved | DAVID FASTIGGI |
| Final | 5/21/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/21/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/21/2026 | Approved | ALEXANDER HANDY |
| Final | 6/18/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 6/18/2026 | Approved | ALEXANDER HANDY |