14130-14132 W GAIN ST 91331
Certificate Information: 14130-14132 W GAIN ST 91331
- Application / Permit
- 25016-20000-15064
- Plan Check / Job No.
- B25VN13020
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12' x 2' ADDITION TO AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). PER WFPP.
- Permit Issued
- Issued on 5/21/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 5/16/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/19/2025 | APPLICANT |
| Issued | 5/21/2025 | APPLICANT |
| CofO in Progress | 7/23/2025 | MICHEL ABAJAN |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/20/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 5/29/2025 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/29/2025 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 6/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 6/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 6/12/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/12/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/16/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/16/2025 | Approved | MICHEL ABAJAN |
| Final | 7/16/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/16/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/16/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/16/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/16/2025 | Approved | MICHEL ABAJAN |
| Final | 7/22/2025 | OK to Issue CofO | MICHEL ABAJAN |