6559 N FALLBROOK AVE 91307
Certificate Information: 6559 N FALLBROOK AVE 91307
- Application / Permit
- 25016-20000-14953
- Plan Check / Job No.
- B25VN12900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan: TENANT IMPROVEMENT AT EXISTING RETAIL, INCLUDING NEW FIXTURES, SHELVING, CHECKOUT LANES AND STORAGE RACKS
- Permit Issued
- Issued on 11/4/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/9/2026
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | VAHAN JIVALAGIAN |
| Corrections Issued | 5/11/2025 | VAHAN JIVALAGIAN |
| Quality Review Completed | 5/15/2025 | OMID HEDAYAT |
| Assigned to Zoning Architect | 5/15/2025 | NICOLE SALEEBA |
| Applicant returned to address corrections | 10/3/2025 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/31/2025 | VAHAN JIVALAGIAN |
| Issued | 11/4/2025 | APPLICANT |
| Permit Finaled | 1/8/2026 | BRIAN KELLY |
Permit Application Clearance Information
| DAS Clearance | Cleared | 10/23/2025 | Samuel Gonzalez |
| Zoning Plan Check | Cleared | 10/24/2025 | NICOLE SALEEBA |
Contact Information
| Contractor | Alliance Builders; Lic. No.: 497113-B | , |
| Engineer | Young,, Bradley Rae; Lic. No.: S4727 | 345 POLLASKY AVENUE CLOVIS, CA 93612 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/5/2025 | Conditional Approval | BRIAN KELLY |
| Final | 12/11/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/11/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 12/18/2025 | Corrections Issued | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 12/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 12/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 1/8/2026 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 1/8/2026 | Approved | BRIAN KELLY |