11671 W CHANDLER BLVD 91601
Certificate Information: 11671 W CHANDLER BLVD 91601
- Application / Permit
- 25016-20000-14709
- Plan Check / Job No.
- B25VN12681
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- INTERIOR REMODEL TO REMOVE WALLS TO CREATE OPEN KITCHEN AND CREATE NEW BATHROOM. EXTERIOR REMODEL TO FILL IN WINDOW, REMOVE AND REPLACE WINDOW, DOOR OF (E) UNITS.
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/22/2026
Permit Application Status History
| Submitted | 5/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/15/2025 | GIOVANNY CHAVEZ |
| Building Plans Picked Up | 5/19/2025 | APPLICANT |
| Plan Check Approved | 6/20/2025 | OMAR GARNICA |
| Issued | 6/20/2025 | APPLICANT |
| Permit Finaled | 4/21/2026 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/20/2025 | NATHAN ROMINE |
| Specific Plan | Cleared | 5/22/2025 | SASHA KASSAB |
| Address approval | Cleared | 6/2/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | WALLIE JONG |
Contact Information
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2025 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 9/26/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 10/15/2025 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 10/16/2025 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 10/21/2025 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 10/23/2025 | Approved | DEANDRE HOFFMAN |
| Final | 3/24/2026 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 3/24/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 4/15/2026 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 4/15/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 4/21/2026 | Permit Finaled | DEANDRE HOFFMAN |
| Smoke Detectors | 4/21/2026 | Approved | DEANDRE HOFFMAN |