11671 W CHANDLER BLVD 91601

Certificate Information: 11671 W CHANDLER BLVD 91601

Application / Permit
25016-20000-14709
Plan Check / Job No.
B25VN12681
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
INTERIOR REMODEL TO REMOVE WALLS TO CREATE OPEN KITCHEN AND CREATE NEW BATHROOM. EXTERIOR REMODEL TO FILL IN WINDOW, REMOVE AND REPLACE WINDOW, DOOR OF (E) UNITS.
Permit Issued
Issued on 6/20/2025
Issuing Office
Current Status
Permit Finaled on 4/22/2026

Permit Application Status History

Submitted 5/6/2025 APPLICANT
Assigned to Plan Check Engineer 5/14/2025 GIOVANNY CHAVEZ
Corrections Issued 5/15/2025 GIOVANNY CHAVEZ
Building Plans Picked Up 5/19/2025 APPLICANT
Plan Check Approved 6/20/2025 OMAR GARNICA
Issued 6/20/2025 APPLICANT
Permit Finaled 4/21/2026 DEANDRE HOFFMAN

Permit Application Clearance Information

Miscellaneous Cleared 5/20/2025 NATHAN ROMINE
Specific Plan Cleared 5/22/2025 SASHA KASSAB
Address approval Cleared 6/2/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/3/2025 WALLIE JONG

Contact Information

Contractor M Y Construction Inc; Lic. No.: 1036168-B 10116 HILLGROVE DRIVE      BEVERLY HILLS, CA 90210
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/30/2025 Conditional Approval JEFFREY DURAN
Wood Frame 9/26/2025 Corrections Issued DEANDRE HOFFMAN
Wood Frame 10/15/2025 Partial Approval DEANDRE HOFFMAN
Insulation 10/16/2025 Approved DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Approved KENNETH ROBERTS
Interior/Exterior Lathing 10/21/2025 Approved KENNETH ROBERTS
Drywall Nailing 10/23/2025 Approved DEANDRE HOFFMAN
Final 3/24/2026 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 3/24/2026 Not Ready for Inspection JEFFREY FULTON
Final 4/15/2026 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved JEFFREY FULTON
Smoke Detectors 4/15/2026 Not Ready for Inspection JEFFREY FULTON
Final 4/21/2026 Permit Finaled DEANDRE HOFFMAN