8816 N HASKELL AVE 91343

Certificate Information: 8816 N HASKELL AVE 91343

Application / Permit
25016-20000-14597
Plan Check / Job No.
B25VN12563
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ACCESSORY LIVING QUARTER INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 5/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2025 APPLICANT
Assigned to Plan Check Engineer 5/9/2025 HAYATO TSUCHIYA
Corrections Issued 5/9/2025 HAYATO TSUCHIYA
Building Plans Picked Up 5/13/2025 APPLICANT
Plan Check Approved 5/20/2025 ALEC MOUSAKHANIAN
Issued 5/21/2025 APPLICANT
CofO in Progress 8/12/2025 JENNIFER RABUCHIN
Permit Finaled 9/4/2025 RUBEN SALAS
CofO Issued 9/4/2025 RUBEN SALAS
Permit Finaled 9/4/2025 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 5/13/2025 RUBEN VASQUEZ
Address approval Cleared 5/17/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/17/2025 LEE GUILBEAUX
Sewer availability Cleared 5/17/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/17/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 6/23/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/23/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/9/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 7/9/2025 Conditional Approval SALVADOR MARTINEZ
HVAC-Rough 7/9/2025 Approved SALVADOR MARTINEZ
MERV13>=Rough 7/9/2025 Approved SALVADOR MARTINEZ
Underground Mechanical 7/9/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 7/11/2025 Approved JENNIFER RABUCHIN
Insulation 7/11/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/21/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 7/21/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 7/21/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/11/2025 Approved JENNIFER RABUCHIN
Final 8/11/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/11/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/11/2025 Approved JENNIFER RABUCHIN