5122 N WILLOW CREST AVE 91601

Certificate Information: 5122 N WILLOW CREST AVE 91601

Application / Permit
25016-20000-14407
Plan Check / Job No.
B25VN12453
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GC 66323(a)(1). WORK DONE PER WFPP.
Permit Issued
Issued on 5/21/2025
Issuing Office
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 MADISON ODELL
Corrections Issued 5/9/2025 MADISON ODELL
Applicant returned to address corrections 5/14/2025 MADISON ODELL
Applicant returned to address corrections 5/15/2025 LUISANGEL VALENZUELA
Plan Check Approved 5/20/2025 MADISON O'DELL
Issued 5/21/2025 APPLICANT
CofO in Progress 2/24/2026 JAVIER RAMOS JR
Permit Finaled 3/11/2026 RUBEN SALAS
CofO Issued 3/11/2026 RUBEN SALAS
Permit Finaled 3/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/12/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 5/12/2025 COLIN LOREDO
Sewer availability Cleared 5/12/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2025 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 5/23/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/23/2025 Approved JOSE AVILA
Footing/Foundation/Slab 5/30/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/17/2025 Partial Approval JOSE AVILA
Special/Order Compliance 6/17/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/23/2025 Corrections Issued JOSE AVILA
HVAC-Rough 6/23/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 6/27/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 6/27/2025 Approved JOSE AVILA
Green Building Rough 6/27/2025 Approved JOSE AVILA
HVAC-Rough 6/27/2025 Approved JOSE AVILA
PLUMBING-Rough 6/27/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 7/1/2025 Conditional Approval JOSE AVILA
Insulation 7/1/2025 Approved JOSE AVILA
Interior/Exterior Lathing 7/1/2025 Approved JOSE AVILA
Drywall Nailing 7/11/2025 Approved JOSE AVILA
Green Building Final 8/7/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 8/7/2025 Approved JOSE AVILA
Pre-Inspection 8/22/2025 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 2/5/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/11/2026 Approved JAVIER RAMOS JR
Final 2/11/2026 Conditional Approval JAVIER RAMOS JR
Green Building Final 2/11/2026 Approved JAVIER RAMOS JR
HVAC-Final 2/11/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 2/11/2026 Approved JAVIER RAMOS JR
Service/Power Release 2/11/2026 Approved JAVIER RAMOS JR
Final 2/24/2026 OK to Issue CofO JAVIER RAMOS JR