11229-11231 N DANUBE AVE 91344

Certificate Information: 11229-11231 N DANUBE AVE 91344

Application / Permit
25016-20000-14234
Plan Check / Job No.
B25VN12323
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 JESSE ARELLANO
Corrections Issued 5/8/2025 JESSE ARELLANO
Building Plans Picked Up 5/13/2025 APPLICANT
Plan Check Approved 5/15/2025 JEROME MAGAT PALMA
Issued 5/15/2025 APPLICANT
CofO in Progress 3/20/2026 JENNIFER RABUCHIN
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/14/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/14/2025 RYAN CASTRO
Sewer availability Cleared 5/14/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 5/14/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2025 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/25/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 6/25/2025 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/30/2025 Approved NICHOLAS TROWBRIDGE
Insulation 7/30/2025 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 9/2/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/29/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/5/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 11/5/2025 Not Ready for Inspection JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 11/5/2025 Corrections Issued JENNIFER RABUCHIN
Sewer 11/5/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/7/2025 Approved NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 11/7/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 11/12/2025 Partial Approval MICHAEL CORTEZ
Insulation 11/13/2025 Corrections Issued CHRISTOPHER MORFIN
Green Building Rough 11/17/2025 Approved JENNIFER RABUCHIN
Insulation 11/17/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/17/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 11/20/2025 Approved JENNIFER RABUCHIN
Shower Pan 11/20/2025 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 11/26/2025 Approved JENNIFER RABUCHIN
Shower Pan 11/26/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 12/1/2025 Partial Approval WILLIAM WREN
ELECTRICAL-Final 1/28/2026 Corrections Issued JENNIFER RABUCHIN
Final 1/28/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/28/2026 Approved JENNIFER RABUCHIN
HVAC-Final 1/28/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/28/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 1/28/2026 Approved JENNIFER RABUCHIN
Final 3/13/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Ready JENNIFER RABUCHIN
ELECTRICAL-Final 3/20/2026 Approved JENNIFER RABUCHIN
Final 3/20/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/20/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/20/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved JENNIFER RABUCHIN