23927-23929 W GILMORE ST 91307
Certificate Information: 23927-23929 W GILMORE ST 91307
- Application / Permit
- 25016-20000-14131
- Plan Check / Job No.
- B25VN12254
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN:CONVERT (E) ATTACHED GARAGE TO JADU PER GC 66323(a)(1) and 66333.
- Permit Issued
- Issued on 7/23/2025
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 5/6/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 5/16/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 6/18/2025 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 7/1/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/14/2025 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/23/2025 | SAMUEL GONZALEZ |
| Issued | 7/23/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | TROY SANDERS |
| CofO in Progress | 3/23/2026 | ROBERT GOLD |
| Permit Finaled | 3/24/2026 | JOHN JANSON |
| CofO Issued | 3/24/2026 | JOHN JANSON |
| Permit Finaled | 3/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/14/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Devart8 Builders Inc; Lic. No.: 1101484-B | , |
| Engineer | Fernandez,, Jose Carlos; Lic. No.: C76349 | 1838 E PRESTWICK AVE FRESNO, CA 93730 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/3/2025 | Partial Approval | TROY SANDERS |
| Sewer | 9/3/2025 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 9/5/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/5/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 9/26/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/26/2025 | Approved | TROY SANDERS |
| Green Building Rough | 9/26/2025 | Approved | TROY SANDERS |
| HVAC-Rough | 9/26/2025 | Approved | TROY SANDERS |
| PLUMBING-Rough | 9/26/2025 | Approved | TROY SANDERS |
| Insulation | 10/10/2025 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 10/17/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Not Ready | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | TROY SANDERS |
| ELECTRICAL-Final | 12/30/2025 | No Access for Inspection | TROY SANDERS |
| Final | 12/30/2025 | No Access for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 2/4/2026 | Approved | TROY SANDERS |
| Final | 2/4/2026 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/4/2026 | Approved | TROY SANDERS |
| HVAC-Final | 2/4/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 2/4/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/4/2026 | Approved | TROY SANDERS |