6510 N MCLENNAN AVE 91406

Certificate Information: 6510 N MCLENNAN AVE 91406

Application / Permit
25016-20000-14077
Plan Check / Job No.
B25VN12204
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. (E) Storage room to be converted into an ADU with Laundry PER GCS65852.2(e)(1)(A) AND PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 04/18/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" CEIS Case Number is 1044129.
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
Issued on 5/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/1/2025 APPLICANT
Assigned to Plan Check Engineer 5/5/2025 CRYSTEL MAALOUF
Corrections Issued 5/6/2025 CRYSTEL MAALOUF
Plan Check Approved 5/13/2025 NGHI SU
Issued 5/15/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/7/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/7/2025 RYAN CASTRO
Sewer availability Cleared 5/7/2025 RYAN CASTRO
Construction near power lines Cleared 5/9/2025 WALTER RAMIREZ
ZI Cleared 5/9/2025 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/27/2025 Corrections Issued MICKEY YAMASHITA
Green Building Rough 5/27/2025 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 5/27/2025 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 5/27/2025 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 5/27/2025 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 11/7/2025 Partial Inspection JOEL GUARDADO
BUILDING-Rough-Frame 1/7/2026 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 1/7/2026 Corrections Issued MICKEY YAMASHITA
Gas Test 1/7/2026 Corrections Issued MICKEY YAMASHITA
Green Building Rough 1/7/2026 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 1/7/2026 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 1/7/2026 Corrections Issued MICKEY YAMASHITA
Sewer 1/7/2026 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 2/25/2026 Partial Approval MICKEY YAMASHITA
Gas Test 2/25/2026 Corrections Issued MICKEY YAMASHITA
HVAC-Final 2/25/2026 Partial Approval MICKEY YAMASHITA
Sewer 2/25/2026 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 4/1/2026 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 4/1/2026 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 4/1/2026 Approved MICKEY YAMASHITA
Gas Test 4/1/2026 Partial Approval MICKEY YAMASHITA
HVAC-Rough 4/1/2026 Conditional Approval MICKEY YAMASHITA
PLUMBING-Rough 4/1/2026 Approved MICKEY YAMASHITA
Sewer 4/1/2026 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 5/7/2026 Conditional Approval MICKEY YAMASHITA
Green Building Rough 5/7/2026 Approved MICKEY YAMASHITA
HVAC-Rough 5/7/2026 Corrections Issued MICKEY YAMASHITA
Insulation 5/7/2026 Approved MICKEY YAMASHITA
PLUMBING-Rough 5/7/2026 Approved MICKEY YAMASHITA
Drywall Nailing 5/14/2026 Conditional Approval JOEL GUARDADO
Shower Pan 5/27/2026 Approved JOEL GUARDADO