10629 N WOODWARD AVE 91040

Certificate Information: 10629 N WOODWARD AVE 91040

Application / Permit
25016-20000-13718
Plan Check / Job No.
B25VN11931
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE TO DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 6/19/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/5/2025 MEL KHACHATOURIAN
Corrections Issued 5/6/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 6/11/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 6/18/2025 ISIS ARGUETA
Issued 6/19/2025 APPLICANT
CofO in Progress 12/17/2025 DAVID ANDERSON
Permit Finaled 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/6/2025 LEE GUILBEAUX
Sewer availability Cleared 5/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/6/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 5/14/2025 GERMAN RODRIGUEZ MENDOZA
Eng Process Fee Ord 176,300 Cleared 5/19/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Hagopyan,, Edmond; Lic. No.: C80143 3300 FOOTHILL BLVD   # 8601    GLENDALE, CA 91214

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/14/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 8/27/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 8/29/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 9/24/2025 Approved WILLIAM WREN
HVAC-Rough 9/24/2025 Approved WILLIAM WREN
Sewer 9/24/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/8/2025 Conditional Approval WILLIAM WREN
PLUMBING-Rough 10/8/2025 Approved WILLIAM WREN
Insulation 10/15/2025 Approved CHRISTOPHER MORFIN
Deputy Wood Construction 10/17/2025 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/21/2025 Corrections Issued DAVID ANDERSON
Drywall Nailing 10/27/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/8/2025 Approved NICHOLAS TROWBRIDGE
Final 12/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Not Required NICHOLAS TROWBRIDGE
Smoke Detectors 12/8/2025 Approved NICHOLAS TROWBRIDGE
Final 12/12/2025 OK to Issue CofO DAVID ANDERSON